Purpose

Called Terry at All American Concrete to discuss the driveway pour and surfaced a sequencing question: should the house-to-garage utility trench (sewer, natural gas, water) be installed before the driveway is poured?

Notes

Sequencing Question Raised

  • Terry asked whether the utility trench should be done first
  • Owner did not know — sequencing not yet decided
  • Concern: if the trench crosses the driveway path or apron area, cutting/patching new concrete after the pour would be far more expensive and visually compromising than running the trench under prepared subgrade beforehand
  • Terry recommended consulting a plumber to determine whether any portion of the trench install (sewer, natural gas, water) requires a licensed plumber and what the correct sequencing is

Plumber Referral

Floor Coating Referral — Still Pending

  • Reminded Terry of the still-outstanding floor coating contractor referral (polyurea/polyaspartic recommendation he mentioned earlier)
  • Terry still has not sent the link — owner awaiting text
  • See 1. Terry’s Recommendation (TBD) - PRIORITY

Decisions

  • Deferred: Driveway-vs-trench sequencing decision — pending input from Brian (plumber) on what work needs licensed install and what sequence is correct
  • No commitment to driveway start date until trench sequence is resolved

Action Items

  • Confirm with Brian whether utility trench must be installed before driveway pour — owner:: Owner — stage:: 6
  • Confirm with Brian which portions of sewer/gas/water trench install require a licensed plumber — owner:: Owner — stage:: 6
  • Follow up with Terry for floor coating contractor contact (still not sent) — owner:: Owner — stage:: 7

Timeline Impact

Previous Schedule

  • All American Concrete previously indicated they can start utility trench work after May 1, 2026 (see Utility Trench Work)
  • Driveway estimate received March 16, 2026 ($14,496.00, Estimate #7689) — no firm pour date

Updated Schedule

  • Driveway pour now gated on resolving trench sequencing with Brian (plumber)
  • If trench must precede driveway: trench install becomes the next milestone, then driveway
  • If trench can be installed after: driveway scheduling can proceed independently

Next Steps

  1. Wait for Brian to return voicemail
  2. When connected, ask about trench-before-driveway requirement and licensed-plumber scope
  3. Update Decisions Log once sequencing is decided
  4. Update Timeline with driveway target once trench sequence is set