Contractor Outreach Action Plan

Current Status (Dec 16, 2025)

Build Status:

  • Exterior shell complete and weathertight (Dec 12)
  • Metal roof, windows, door installed
  • Hershberger crew on Christmas break until Dec 29
  • Siding installation pending (Versetta Ledgestone + LP SmartSide)

Contractors Already Engaged:

  • Hershberger’s (Marcus) - Framing/exterior - ACTIVE
  • SLS Electric (Steve) - 200A service - SELECTED ($4,610 quote)

Why Schedule Now?

TradeReason for Early Outreach
Floor CoatingSeasonal business - Spring is peak season; early booking = earliest slot after winter thaw
InsulationNeeded before drywall; winter is slower season = better availability
HVACLinesets must be routed before insulation; lead time on equipment
DrywallDependent on insulation; get in queue early for Feb-Mar window

Work Sequence (Critical Path)

1. Exterior Siding (Dec 29+) ─────────────────────────────┐
                                                          │
2. Electrical Rough-In (SLS Electric) ────────────────────┤
                                                          │
3. HVAC Rough-In (linesets through walls) ────────────────┤
                                                          ▼
4. Insulation (after all penetrations) ───────────────────┐
                                                          │
5. Insulation Inspection ─────────────────────────────────┤
                                                          ▼
6. Drywall (hang, tape, finish) ──────────────────────────┐
                                                          │
7. Electrical/HVAC Trim-Out ──────────────────────────────┤
                                                          │
8. Paint ─────────────────────────────────────────────────┤
                                                          ▼
9. Floor Coating (last - needs clear floor, 90+ day cure)

Action Plan by Week

Week of Dec 16-22 (NOW)

Floor Coating - HIGH PRIORITY:

  • Call Terry (concrete contractor) to get recommended coating company contact
  • Research backup options while waiting

Insulation:

  • Web search for Clare/Mt. Pleasant insulation contractors
  • Check Google reviews, BBB ratings
  • Create shortlist of 3-5 candidates

HVAC:

Week of Dec 23-29 (Christmas Week)

Limited Activity Expected - Holiday Week

  • Continue online research
  • Draft scope documents for each trade
  • Prepare photos/drawings to share with contractors

Week of Dec 30 - Jan 5

Floor Coating:

  • Contact Terry’s recommendation (if info received)
  • Contact Garage Floor Coating of Michigan (Jeremy, 989-698-6566)
  • Contact One Day Custom Floors (Chris, 810-730-1715)
  • Request availability for March site visit, April-May install

Insulation:

  • Begin calling insulation contractor candidates
  • Schedule January site visits
  • Share Insulation Strategy

HVAC:

  • Begin calling HVAC contractor candidates
  • Discuss Manual J load calculation
  • Schedule January site visits

Week of Jan 6-12

Drywall:

  • Begin calling drywall contractor candidates
  • Share scope (5/8” Type X ceiling, Level 4 finish)
  • Schedule January site visits

All Trades:

  • Follow up on any unanswered calls
  • Confirm site visit appointments

Weeks of Jan 13-31

Site Visits & Quotes:

  • Host site visits for all trades
  • Collect written quotes
  • Check references
  • Make contractor selections

Contractor Contact Summary

Floor Coating

CompanyContactPhoneStatus
Terry’s RecommendationTBDTBDAwaiting info from Terry
Garage Floor Coating of MIJeremy(989) 698-6566Not contacted
One Day Custom FloorsChris(810) 730-1715Not contacted
Garage Force Michigan-Website onlyNot contacted

Tracking: Floor Coating Contractors

Insulation

CompanyContactPhoneStatus
TBD--Need to identify candidates

Tracking: Insulation Contractors

HVAC (Mini-Split)

CompanyContactPhoneStatus
TBD--Need to identify candidates

Tracking: HVAC Contractors

Drywall

CompanyContactPhoneStatus
TBD--Need to identify candidates

Tracking: Drywall Contractors

Electrical (Already Selected)

CompanyContactPhoneStatus
SLS Electric LLCSteve-SELECTED - $4,610

Tracking: Electrical Contractors


Target Timeline

TradeQuote ByInstall Window
ElectricalDoneJan-Feb 2026 (TBD with Steve)
HVAC Rough-InJan 31Feb 2026 (before insulation)
InsulationJan 31Feb 2026
DrywallJan 31Feb-Mar 2026
Floor CoatingMar 15Apr-May 2026

Budget Planning

TradeEstimated RangeNotes
Electrical$4,610SLS Electric quote accepted
Insulation$1,500-3,000Depends on DIY vs. pro
HVAC (Mini-Split)$5,000-10,000Depends on system size
Drywall$2,500-4,500Professional install
Floor Coating$4,500-6,500Polyurea/polyaspartic
Total Estimate$18,100-28,610Interior completion trades

Key Contacts to Make This Week

  1. Terry (Concrete) - Get floor coating recommendation
  2. Steve (SLS Electric) - Confirm installation scheduling
  3. Marcus (Hershberger’s) - Confirm Dec 29 return for siding