Attendees

  • Marcus (Hershberger’s)
  • Dan Gahagan

Discussion Summary

Framing Materials Status

Marcus confirmed that framing materials are currently on the way to the site.

Timeline Update

Framing start date: Approximately 2 weeks from 2025-11-04 (target: ~2025-11-18)

Materials delivery expected shortly, with framing work to commence once materials arrive and foundation concrete cure is complete.

Next Steps

  1. ⧗ Materials delivery to site
  2. ⧗ Begin wall framing (estimated 2025-11-18)
  3. ⧗ Mechanical room walls and layout finalization
  4. ⧗ Upstairs framing and floor decking