🎉 INITIAL BUILD COMPLETE — January 21, 2026
Hershberger’s construction contract complete. All contracted work finished:
- ✅ 24’×40’×10’ stick-built garage shell with loft
- ✅ Metal roof, vinyl siding, Versetta Ledgestone accents
- ✅ All 8 windows and entry door installed
- ✅ Three 8’×9’ insulated garage doors with Genie 6170H-B openers (battery backup)
- ⏳ Dumpster cleanup pending — Hershberger’s returning soon
Reference: Jan 21 Photos | Timeline
Contract status (as of 2025-10-25)
- Total: $68,400 with Hershberger’s Amish Builders for the full 24’x40’x10’ stick-built garage shell.
- Payments: 20,000 paid 2025-10-25 (contract signing); 21,800 at completion.
- Scope highlights: 8”x42” rat wall, 4” slab over 2” Creatherm with 1/2” PEX radiant loops (pressure test), embedded sleeves for sewer/water/electric/fiber, Burnished Slate metal roof (snow guard front), Dutch Lap Herringbone siding, white aluminum soffit/fascia, Genie 6170 jackshaft openers on (2) 9’x8’ insulated OHDs, Versetta Ledgestone (Plum Creek) between doors, enclosed stair to loft with OSB floor/wainscot and mechanical closet.
- Excavation/dig slated to start Thursday 2025-10-16; verify lift bay PEX-free pads before pour (not yet in contract language).
- See also: Products Used for complete product specifications and links
Open coordination items
- Ask about pouring small slab for mini-split heat pump (still needed outside contract scope).
- Confirm insurance carrier notified prior to dig.
- Coordinate utility trenching budget (still estimate 10k); consider tackling basement rear wall repair while yard is open.
- Confirm driveway allowance remains 15k placeholder outside current contract.
Related: Utilities & Conduits
Sequencing Notes
- Pour radiant slab and install subslab rigid insulation before wall framing where possible.
- Coordinate PEX layout photos/sketches prior to pour; keep lift column pads PEX-free.
Construction Progress (Updated 2025-10-30)
- ✓ Excavation completed (Oct 20)
- ✓ Foundation forms and rat wall perimeter completed (Oct 20)
- ✓ 2” Creatherm under-slab insulation installed - 110 sheets 9x4 (Oct 22)
- ✓ PEX radiant heating loops installed with manifold (Oct 22)
- ✓ Initial utility sleeves positioned (water, sewer, electric, fiber, gas) (Oct 22)
- ✓ Pressure testing radiant system at 60-70 PSI (Oct 22)
- ✓ City inspection of PEX in-floor heating - PASSED (Oct 23)
- ✓ Mechanical permit inspection requirement satisfied (Oct 23)
- ✓ Notified Marcus (contractor) of inspection approval (Oct 23)
- ✓ Delivered $20,000 payment to Hershbergers per contract (Oct 25)
- ✓ Confirmed with Marcus that Terry (cement contractor) will install utility conduits before pouring concrete (Oct 25)
- ✓ Exterior perimeter insulation installed (Oct 29)
- ✓ Fiberglass rebar grid installation completed (Oct 29)
- ✓ All utility conduits installed through slab (Oct 30):
- Water line (2” PVC conduit)
- Sewer line (3” PVC conduit)
- Natural gas line (2” PVC conduit)
- Electric service (2” PVC conduit)
- Low voltage/data (2” PVC conduit for fiber optic, coax, network)
- ✓ Concrete foundation pour completed (Oct 30)
- ✓ Initial concrete finishing work completed (Oct 30)
- ✓ ½” PEX conduit for future slab sensor installed (blue PEX tube routed through EZ loop with in-floor heating lines - visible in photos)
- ✓ Control joint saw cuts completed (Oct 31)
- ✓ Wooden perimeter forms removed (Oct 31)
- ✓ Perimeter backfilled with dirt (Oct 31)
- ✓ Radiant heating system pressure testing completed and passed (Oct 31)
- ✓ Foundation finishing complete (Oct 31)
- ✓ Temporary diesel air heaters tested for backup and pre-insulation heat (Nov 1)
- ✓ Family initials added to slab edge as commemorative milestone (Nov 1)
- ✓ Final site grading completed by concrete crew (Nov 3)
- ✓ Concrete cure period complete (Nov 18 - 19 days since pour)
- ✓ Roof trusses delivered by Letherer Truss Inc. - Job #123907 (Nov 18):
- 41 engineered trusses (5,359 lbs total)
- 4x LVL beams (1¾” x 11⅞” 2.0E)
- 12x structural hardware pieces (hangers/connectors)
- Complete engineering documentation package received
- T.P.I. bracing instructions included
- Trusses staged on cured slab
- ✓ Framing kickoff (Dec 3): First-floor walls stood with LVL headers, OSB sheathing staged, joist hangers installed
- ✓ Roof trusses set (Dec 4): All roof trusses installed with Gehl RT215 track loader assist
- ✓ Dormer framing (Dec 4): Dormer wall panels framed and stood on roof structure
- ✓ Loft floor system (Dec 4): Joists installed with Simpson hangers and blocking; Titebond construction adhesive applied (glue-and-screw method)
- ✓ Roof sheathing complete (Dec 8): Main roof planes fully sheathed; sheathing lifted to dormer level via skid steer with forks
- ✓ Weatherproofing applied (Dec 8): Synthetic underlayment installed on main roof and dormer roofs; Tyvek house wrap on dormer faces; starter course and taped seams at eaves/gables
- ✓ Metal roof installation in progress (Dec 11): Standing-seam charcoal panels installed on main roof planes and dormer returns; crew working with ladders and roof jacks; panels nearly complete by end of day; ridge vent and remaining trim pending
- ✓ Windows delivered (Dec 11): 8 windows from ABC Supply (Order #580876):
- 7x Premium Designer NC DH 35½” × 35½” (fiberglass full screen, double lock)
- 1x Egress unit 39½” × 59½” (Premium Designer NC DH)
- ✓ Exterior door delivered (Dec 11): Half-lite exterior door with grids staged for installation
- ✓ Stone veneer panels delivered (Dec 11): Versetta Ledgestone (Plum Creek) decorative stone panels for base/wainscot between garage doors
- ✓ Siding prep materials delivered (Dec 11): Tyvek HomeWrap, Dupont flashing tape, coil stock/trim, fasteners all staged inside
- ✓ EXTERIOR SHELL COMPLETE (Dec 12): Metal roof fully installed on main roof and dormers; all 8 windows installed (7x 35½”×35½” + 1x egress 39½”×59½”); main entry door (half-lite) set at right bay; vented soffits installed along front eave; Tyvek HomeWrap fully covering all wall surfaces. Building is now weathertight and ready for siding installation. See Dec 12 Photos (10 photos).
- ✓ Christmas break begins (Dec 16): Called Marcus; crew taking break until December 29, 2025 to finish exterior siding work. Building is weathertight so no urgency. See 2025-12-16 - Call - Marcus Christmas Break Schedule.
- ✓ Electrical trenching attempted (Dec 18): SLS Electric arrived to begin underground power line. Wire successfully buried along house foundation (thawed ground from building heat). Open area has ~10” frozen ground — largest backhoe made only 3 feet in 30 minutes. Trenching postponed to spring 2026. Wire spool stored at terminus. See Dec 18 Photos (6 photos).
- ✓ Loft interior documentation (Dec 20): Site visit during Christmas break to document loft condition. Photos captured: loft floor, dormer windows, knee walls, stair opening. Loft Flooring Plan created with LVP research. See Dec 20 Photos (8 photos).
- ✓ Front siding complete & door openings modified (Jan 13): Front wall siding and Versetta Ledgestone installed; garage door openings modified from 7’ to 8’ height to match correctly-ordered doors; snow stops and sewer vent installed. See Jan 13 Photos (3 photos).
- ✓ Electrical ground thawing (Jan 15): SLS Electric deployed passive curing blankets to thaw frozen ground for trench completion; 2-4 week estimate. See Jan 15 Photos (1 photo).
- ✓ 🎉 GARAGE DOORS INSTALLED — INITIAL BUILD COMPLETE (Jan 21): All three 8’×9’ insulated white garage doors with window panels installed; three Genie 6170H-B Professional Line openers with battery backup installed and tested (doors operational despite no grid power). Hershberger’s construction contract complete — only dumpster cleanup remaining. See Jan 21 Photos (8 photos).
- ⧖ Next: Dumpster cleanup (Hershberger’s returning soon), electrical service completion (ground thawing in progress)
Video Documentation
See Construction Videos for time-lapse videos of the construction process.
Available time-lapses:
- Foundation Dig & Site Prep (Oct 20, 2025)
- Creatherm & PEX Installation (Oct 22, 2025)
Photo Documentation (Oct 22, 2025)
- Aerial View - Insulation Complete (5:41 PM)
- Aerial View - Second Angle (6:51 PM)
- Ground Level Overview (7:06 PM)
- Foundation Perimeter & Utility Sleeves (7:06 PM)
- PEX Manifold Installation (7:07 PM)
- Pressure Test Gauge - 60-70 PSI (7:07 PM)
Drone Aerial Photography (Oct 25, 2025)
- Foundation Insulation - Direct Overhead View
- Garage Foundation and House - Context View
- Complete Property Overview - High Altitude
- Full Property and Neighborhood - Wide Perspective
Note: Blue PEX line visible in drone photos is the slab temperature sensor conduit installed by owner (see Decisions - Slab Sensor Conduit).
Drone Aerial Photography - Exterior Insulation & Rebar (Oct 29, 2025)
- Exterior Slab Insulation and Fiberglass Rebar - Aerial View 1
- Exterior Slab Insulation and Fiberglass Rebar - Aerial View 2
- Exterior Slab Insulation and Fiberglass Rebar - Aerial View 3
- Exterior Slab Insulation and Fiberglass Rebar - Aerial View 4
- Exterior Slab Insulation and Fiberglass Rebar - Aerial View 5
- Exterior Slab Insulation and Fiberglass Rebar - Aerial View 6
Photo Documentation - Concrete Pour (Oct 30, 2025)
- Cement Truck Arrival (9:24 AM)
- Concrete Pour in Progress - Aerial View (9:31 AM)
- Completed Slab - Finished Surface (11:45 AM)
- Utility Conduits Through Slab - Close-Up Detail (11:45 AM)
- Completed Slab with Utility Conduits - Wide View (11:45 AM)
Video Documentation:
- Real-time concrete pour (~1 hour): Construction Videos
Photo Documentation - Post-Pour Finishing (Oct 31, 2025)
- Slab Finishing Complete - Saw Cuts and Perimeter Fill (1:50 PM)
- Finished Slab with Conduits - Northwest View (1:51 PM)
- Radiant Heating System Pressure Test (1:51 PM)
Photo Documentation - Final Site Grading (Nov 3, 2025)
- Site Grading Progress (1:54 PM)
- Grading Detail View (1:54 PM)
- Site Grading After Concrete Crew (4:15 PM)
Photo Documentation - Truss Delivery (Nov 18, 2025)
Engineering Documents:
- Complete Truss Engineering Drawings (8-page packet)
- Layout drawing with truss placement (24’ x 40’)
- Detailed engineering for all truss types (PLY-1, PLY-2, mono, girders)
- Load calculations and bearing reactions
- Connection specifications
- Loading Ticket & Inventory (Job #123907)
- 41 WoodTruss components (13 attic, 4 girders, 4 special, 10 common, 4 mono)
- Total weight: 5,359 lbs
- Hardware inventory (HGUS48, MUS26, LUS24 connectors)
- T.P.I. bracing instructions included
Photo Documentation - Framing Kickoff (Dec 3, 2025)
Weather: Overcast, 18-24°F. Snow cover on site from overnight accumulation; cold but workable conditions for framing kickoff.
- Early Morning Lumber Delivery (7:21 AM)
- First Floor Walls Rising (1:12 PM)
- Framing Progress from House Window (1:13 PM)
- Ridged Sill Plate Gasket (3:23 PM)
- Interior Bracing and Bottom Plate Anchor (3:29 PM)
- Front Elevation Framing with Center Bay Bracing (3:30 PM)
- Framing Progress Checkpoint (3:37 PM)
- Materials Invoice (Adhesive, OSB, Foam) (3:42 PM)
- Materials Invoices (Framing Lumber & Hardware) (3:42 PM)
- OSB Stacks Staged for Framing (3:43 PM)
- Framing Lumber on Sawhorses (3:43 PM)
- OSB Grade Stamp (3:43 PM)
- Joist Hanger Hardware Box with Invoices (3:44 PM)
- Simpson LUS28Z Joist Hanger (3:44 PM)
- Simpson HGUS48 Hanger (3:44 PM)
Photo Documentation - Roof Trusses & Dormer Framing (Dec 4, 2025)
Weather: Overcast clearing to partly sunny, then clear by afternoon. Temperature range 10-21°F, NW winds 5-10 mph. Snow cover on site from Dec 1-3 storms; ideal visibility for photography as skies cleared.
Morning - Equipment & Truss Setting:
- Gehl RT215 Track Loader Arrival (7:57 AM)
- Hydraulic Auger Attachment Staged (7:57 AM)
- Truss Set with Loader Assist (9:15 AM)
Midday - Roof Trusses Complete:
Afternoon - Dormer & Loft Framing:
- Afternoon Framing Overview from House (2:53 PM)
- Dormer Framing in Place (2:56 PM)
- Loft Joists and Hanger Installation (2:57 PM)
- Titebond Construction Adhesive - Glue-and-Screw Subfloor (2:57 PM)
- Interior Loft Framing Progress (2:58 PM)
- RT215 Control Console Detail (3:11 PM)
Photo Documentation - Roof Sheathing & Weatherproofing (Dec 8, 2025)
Weather: Clear winter sun to partly cloudy, 20-26°F; full snow cover on site; excellent conditions for roofing work.
Photo Documentation - Metal Roof & Material Delivery (Dec 11, 2025)
Weather: Cloudy, 26-30°F; cold winter afternoon with snow cover; good conditions for roofing work.
Roofing Progress:
- Crew Installing Standing-Seam Roof (12:13 PM)
- Metal Roof Nearly Complete - Front Elevation (4:50 PM)
- Dormer Roof Tie-In Closeup (4:50 PM)
Material Deliveries Staged Inside:
- Egress Window Unit Delivered (4:52 PM)
- Stack of Standard Windows (7x) (4:52 PM)
- Exterior Door Delivered (Half-Lite) (4:51 PM)
- Decorative Stone Panels Delivered (4:51 PM)
- Tyvek HomeWrap Roll Onsite (4:52 PM)
- Dupont Flashing Tape Delivery (4:51 PM)
- Housewrap, Trim, and Fasteners Staged (4:52 PM)
- Interior Staging Overview (4:53 PM)
Roofing Materials:
- Vent (4:50 PM)
- Roofing Hardware and Foam Closures (4:53 PM)
- Ridge Vent Foam and Membranes (4:53 PM)
- [[pictures/PXL_20251211_215329510.md|#10 x 2.5” Roof Screws with SS Washers (4:53 PM)]]
Photo Documentation - Exterior Shell Complete (Dec 12, 2025)
Weather: Partly cloudy to overcast, 30°F (feels like 23°F); snow cover on ground; cold but clear conditions for final exterior work.
Major Milestone: Building is now weathertight — metal roof complete, all windows and door installed, Tyvek wrapped.
Exterior Views:
- Front Elevation - Exterior Shell Complete
- Left Side Elevation with Entry Door
- Right Side Elevation - Windows Installed
- Rear Elevation - Dormer Windows
- Front Corner - Roof and Soffit Detail
- Metal Roof Ridge Cap and Vent
- Vented Soffit Installation
- Entry Door - Half-Lite with Grids
- Window Installation Detail
- Interior View - Daylight Through Windows
Photo Documentation - Electrical Trenching Attempt (Dec 18, 2025)
Weather: Cloudy, 50°F — warm day but deep ground frost persisted in open areas (~10” frozen).
Work Attempted: SLS Electric arrived to begin underground electrical trenching from house to garage.
What Was Completed:
- Wire buried along house foundation (ground thawed from building heat transfer)
- ~6-8 ft of wire left above ground at house meter for panel connection
What Was Delayed:
-
Open area between house and garage has ~10” frozen ground
-
Largest available backhoe made only 3 feet of progress in 30 minutes
-
Decision: Postpone to spring 2026 — wire spool stored at terminus
Photo Documentation - Loft Interior (Dec 20, 2025)
Weather: Clear to partly cloudy, 28-35°F; good conditions for site documentation.
Purpose: Site visit during Christmas break to document current loft interior condition and support Loft Flooring Plan research.
- Loft Floor - OSB Subfloor Overview
- Dormer Window from Interior
- Knee Wall Framing Detail
- Stair Opening to Main Floor
- Loft Space Looking West
- Loft Space Looking East
- Dormer Interior with Window
- Overall Loft Layout
Related: Loft Flooring Plan — LVP flooring research for home theater and apartment-ready finish
Photo Documentation - Front Siding Complete & Door Opening Modifications (Jan 13, 2026)
Weather: Overcast, 30s°F. Cold winter afternoon with snow cover.
Work Completed:
-
Front wall siding installation (delayed since Jan 2 due to missing stone panel)
-
Versetta Ledgestone stone veneer panels on all garage door columns
-
Snow stops installed on roof above entry door
-
Sewer vent stack routed through roof
-
Garage door openings modified from 7’ to 8’ height
-
Completed Front Elevation with Siding and Snow Stops (1:00 PM)
Photo Documentation - 🎉 Garage Door Installation Complete (Jan 21, 2026)
Weather: Cloudy, 30°F (feels like 21°F with wind chill). Snow cover on ground.
Major Milestone — INITIAL BUILD COMPLETE:
- All three 8’×9’ insulated white garage doors with window panels installed
- Three Genie 6170H-B Professional Line openers installed (with battery backup)
- Doors tested and operational using battery backup (no grid power yet)
- Hershberger’s construction contract complete
Installation Progress (Morning):
- Interior View - Installation in Progress (9:46 AM)
- Interior View - Alternate Angle (9:46 AM)
- Exterior - Two Doors Installed (9:48 AM)
- Third Door Panels Staged (9:49 AM)
- All Three Doors Complete - Elevated View (10:17 AM)
Completed Installation (Afternoon):
- Completed Garage - Front Elevation (2:43 PM)
- All Three Doors - Interior View (3:20 PM)
- Door Operational Test - Battery Backup Working (3:21 PM)
Pending: Hershberger’s returning with dumpster for scrap pile cleanup