Attendees

  • Contractor (Hershberger’s)
  • Dan Gahagan

Discussion Summary

Utility Conduits

Contractor confirmed that cement contractor will return to complete installation of all utility conduits before concrete pour:

  • Water line
  • Sewer line
  • Natural gas line
  • Electric service
  • 2” empty conduit for future low voltage connections (fiber optic, coax for TV, network wires from house to garage)

PEX Pressure Test & Inspection

  • PEX radiant system ready for inspection
  • City inspector scheduled for Wednesday, October 29th, 2025
  • Inspector is currently very busy but has confirmed the appointment
  • Concrete pour scheduled after inspection approval

Slab Temperature Sensor

  • Plan to pick up 25’ of ½” PEX this afternoon to route slab temperature sensor conduit
  • Will be installed before inspection

Next Steps

  1. ✓ Schedule city inspection (completed - Oct 29 confirmed)
  2. ⧗ Pick up 25’ of ½” PEX for slab sensor conduit
  3. ⧗ Install slab sensor conduit
  4. ⧖ City inspection on Oct 29
  5. ⧖ Complete utility conduit installations (after inspection approval)
  6. ⧖ Concrete pour (after utility conduits complete)