Inspection Details

  • Date: October 23, 2025
  • Inspector: City Building Inspector
  • Type: Mechanical permit - PEX in-floor radiant heating
  • Result: ✓ PASSED

Summary

City inspector stopped by and approved the PEX in-floor heating installation. This inspection was a required step for the mechanical permit and clears the way for the cement contractor to proceed with final utility conduit installations and concrete pour.

Actions Taken

  • ✓ Inspector approved PEX radiant heating system
  • ✓ Called and left message for Marcus (contractor) confirming inspection approval

Next Steps

  1. Cement contractor can now proceed with completing all utility conduit installations:
    • Water line
    • Sewer line
    • Natural gas line
    • Electric service
    • 2” empty conduit for future low voltage connections
  2. Install ½” PEX conduit for slab temperature sensor
  3. Rebar/wire mesh installation
  4. Concrete slab and rat wall pour

Notes

This inspection was originally scheduled for Wednesday, October 29th but the inspector was able to stop by early on October 23rd and approve the work. This is excellent news as it allows the project to proceed ahead of schedule.