Attendees

  • Marcus (Hershberger’s)
  • Dan Gahagan

Purpose

  • Deliver contract payment as required
  • Coordinate utility conduit installation before concrete pour
  • Confirm mechanical inspection approval acknowledgment

Actions Taken

Payment Delivery

Payment amounts redacted for privacy

  • Payment delivered on schedule per contract terms

Conduit Installation Coordination

  • ✓ Spoke with Marcus about ensuring Terry (cement contractor) will install utility conduits before pouring concrete
  • ✓ Marcus confirmed Terry will install all conduits before pour
  • Utility conduits to be installed:
    • Water line
    • Sewer line
    • Natural gas line
    • Electric service
    • 2” empty conduit for future low voltage (fiber optic, coax, network from house to garage)

Inspection Acknowledgment

  • ✓ Verified Marcus received notification that mechanical inspection for PEX in-floor heating passed on Oct 23
  • Marcus confirmed he was aware inspection passed

Schedule

  • Terry (cement contractor) expected onsite Monday, Tuesday, or Wednesday this week (Oct 28-30)
  • Work to complete:
    1. Install all utility conduits
    2. Install rebar/wire mesh
    3. Pour concrete slab and rat wall