Purpose

Called Marcus to check on crew scheduling for exterior work completion.

Notes

Christmas Break Schedule

  • Crew is taking Christmas break
  • Earliest return date: December 29, 2025
  • Crew will return after the holiday to finish exterior work

Remaining Exterior Work

  • Siding installation (Versetta Ledgestone and LP SmartSide)
  • Any remaining trim and exterior finish details

Timeline Impact

Previous Schedule

  • Exterior work (siding) was expected to continue through December
  • Building shell completed and weathertight as of Dec 12

Updated Schedule

  • Crew on Christmas break: Dec 16-28 (approximate)
  • Earliest return: December 29, 2025
  • Exterior siding completion pushed to late December/early January

Reasoning for Adjustment

  • Standard holiday break for crew
  • Building is weathertight so no urgency for exterior completion

Action Items

  • Follow up with Marcus week of Dec 29 to confirm crew return