Purpose
Called Marcus to check on crew scheduling for exterior work completion.
Notes
Christmas Break Schedule
- Crew is taking Christmas break
- Earliest return date: December 29, 2025
- Crew will return after the holiday to finish exterior work
Remaining Exterior Work
- Siding installation (Versetta Ledgestone and LP SmartSide)
- Any remaining trim and exterior finish details
Timeline Impact
Previous Schedule
- Exterior work (siding) was expected to continue through December
- Building shell completed and weathertight as of Dec 12
Updated Schedule
- Crew on Christmas break: Dec 16-28 (approximate)
- Earliest return: December 29, 2025
- Exterior siding completion pushed to late December/early January
Reasoning for Adjustment
- Standard holiday break for crew
- Building is weathertight so no urgency for exterior completion
Action Items
- Follow up with Marcus week of Dec 29 to confirm crew return
Related Notes
- Timeline - Project timeline updated with Christmas break