Purpose
Marcus called to confirm framing crew mobilization timeline.
Notes
Framing Start Confirmed
- Confirmed start window: Tuesday December 2nd (afternoon) or Wednesday December 3rd (morning)
- This aligns with the previously communicated target date of December 3, 2025
- Crew will begin framing work as soon as they arrive
Timeline Impact
Previous Schedule (from Nov 18 call)
- Target start: December 3, 2025
- Follow-up confirmation expected by Nov 26
Confirmed Schedule
- Framing start: Tuesday Dec 2 (PM) or Wednesday Dec 3 (AM)
- Schedule confirmed as expected
Action Items
- Confirm start date with Marcus if no call received by Nov 26 ✓ (Marcus called)
- Complete WRB/venting confirmation call before framing begins (see 2025-12-01 - Call - Marcus WRB and Venting Confirmation)
- Ensure documentation bin is placed onsite before crew arrives
Related Notes
- 2025-11-18 - Call - Marcus Framing Schedule Update - Previous call establishing Dec 3 target
- 2025-12-01 - Call - Marcus WRB and Venting Confirmation - Scheduled pre-framing verification call
- Timeline - Project timeline updated with confirmed start