Builder Conversation - January 1, 2026

Brief conversation with Hershberger’s crew during site visit.

Key Points

Siding Progress

  • West and north walls 100% complete
  • Front and south walls in progress; upper gable sections remaining
  • Completion expected tomorrow (January 2)

Stone Panel Issue

  • One stone panel arrived cracked
  • Could not complete stone column work today
  • Crew will pick up replacement panel tomorrow and finish stone section

Exterior Outlet Accommodation

  • Crew will leave a gap in the siding for an exterior outlet
  • Location: Above the stone siding, between entry door and third bay garage door
  • Electrician (SLS Electric) will install outlet in this prepared opening

Electrical Fixtures

  • Electrician will install soffit fixtures and lights (not the framing crew)
  • Coordinates with SLS Electric scope of work

Cleanup Plan

  • Crew renting a dumpster to clean up scrap materials after build is completed
  • Owner requested to collect useful scraps for spare building materials before disposal
  • Crew agreed — less work for them and materials won’t be wasted

Schedule

  • January 2: Siding completion + stone panel replacement
  • January 6: Garage door and opener installation (final task)