Under-Slab Insulation Complete - Second Aerial View

Under-Slab Insulation Second Aerial View

Photo Details

  • Date: October 22, 2025
  • Time: 6:51 PM (approaching dusk)
  • Weather: Light to moderate drizzle, 47-51°F. Wet conditions visible.
  • Phase: Foundation - Under-slab insulation installation complete
  • Location: 309 E. 7th St., Clare, MI
  • View: Aerial/elevated view from different angle

Description

This second aerial photo, taken about an hour after the previous one, shows the completed Creatherm insulation installation from a slightly different perspective, with late afternoon lighting highlighting the installation details.

Visible Elements

  • Creatherm Insulation Coverage:
    • Bright orange foam panels with white stripes covering entire slab area
    • Two square openings for thickened concrete pads (future 2-post car lift foundation)
    • Consistent panel layout and alignment
    • Clean installation with tight seams between panels
    • PEX loops visible on left side in mechanical room area for future boiler connections
  • Foundation Perimeter:
    • Wooden form boards defining the slab boundaries
    • Dark perimeter insulation visible along edges
    • Excavated trench around foundation perimeter
  • Site Context:
    • Red truck partially visible in lower right
    • Sand/gravel stockpile on left side of property
    • White house with chain-link fence in background
    • Natural wood privacy fence on right boundary
    • Dramatic fall foliage with vibrant orange, red, and yellow trees
    • Partly cloudy sky with blue patches and white clouds
  • Lighting:
    • Late afternoon sun creating longer shadows
    • Softer lighting compared to midday photos

Technical Details

The completed insulation installation shows:

  • 110 sheets of 9x4 Creatherm as specified in delivery invoice
  • 2-inch thickness for R-10 thermal resistance under slab
  • Proper coverage with no visible gaps or missing sections
  • Utility penetrations properly planned and cut
  • Perimeter foam installed for frost protection

Construction Timeline Context

This photo was taken approximately:

  • 2 days after the material delivery (Oct 21)
  • 2-3 days after excavation and forming (Oct 20)
  • Shows the foundation ready for the next critical phase: PEX tubing installation