Decision: Electrical Service Now, Other Utilities Spring 2026

Date: 2025-11-07 Area: Utilities, Winter Construction Strategy Status: Confirmed Priority: Critical (affects winter construction timeline)


Summary

Install electrical service only during winter 2025-26. Defer gas, water, sewer, and low-voltage utilities to spring 2026 for installation in a single shared trench.


Decision

Winter 2025-26 (Now - February 2026):

✅ Install 200A electrical service immediately

  • Route: House SW corner → Garage (separate dedicated trench)
  • Licensed electrician pulls 200A wire through existing 2” PVC conduit
  • 200A panel in garage, 100A initial connection at house
  • Target energization: Mid-December 2025

Spring 2026 (March-May):

✅ Install all other utilities together in single shared trench

  • Gas (1” PE pipe for boiler + future appliances)
  • Water (3/4” PEX supply line)
  • Sewer (3” PVC to house stack)
  • Low-voltage (2” conduit for fiber/network)
  • Route: House connection point → Garage (separate path from electrical)
  • Single excavation, single permit, coordinated installation

Rationale

Why Two Separate Approaches Work

Routing Reality: Per Utilities & Conduits, utilities follow two completely different underground paths:

  1. Trench 1 (Electrical): House SW corner → Garage

    • Separate path per electrician recommendations
    • Different burial depth requirements
    • Independent timeline and contractor
    • Can be installed NOW without affecting other utilities
  2. Trench 2 (Gas/Water/Sewer/Low-Voltage): House connection point → Garage

    • Shared trench for cost efficiency
    • Similar burial depths (all need 42” for frost protection)
    • Coordinated installation by plumber + gas fitter
    • Best installed together in single excavation

Key Insight: Installing electrical service now does NOT require digging the shared utility trench. They are physically separate routes.

Cost Benefits

ApproachCost Impact
Electrical now, others springOne electrical trench + one shared trench = 2 total excavations
All utilities now (separate)Electrical trench + gas trench + water trench + sewer trench = 4+ excavations
Rush everything nowEmergency rates during peak season + winter excavation challenges

Savings:

  • ✅ Single shared trench saves ~$2,000-4,000 in excavation costs
  • ✅ Spring contractor availability = better rates than Dec-Jan peak season
  • ✅ One permit/inspection for shared trench instead of multiple

Timeline Benefits

Winter 2025-26 Focus:

  • ✅ Electrical service provides power for construction (tools, lights)
  • ✅ VEVOR diesel heaters adequate for construction work (40-50°F tested Nov 1)
  • ✅ Shell work continues (roof, siding, windows, doors)
  • ✅ Mechanical room framing/insulation/drywall completed
  • ✅ No dependency on gas service for progress

Spring 2026 Benefits:

  • ✅ Better contractor availability (Mar-Apr vs Dec-Jan peak season)
  • ✅ Easier excavation (ground thawed, no frozen soil)
  • ✅ Boiler operational when most needed (finish work benefits from heat)
  • ✅ Radiant heat helps drywall finishing, painting, detail work

Practical Benefits

What Electrical Service Enables:

  • 💡 Permanent lighting in garage
  • 🔌 Power outlets for construction tools
  • 🔥 Supplemental electric space heaters if needed (backup to VEVOR)
  • 🏗️ Future equipment testing (lift, compressor, etc.)
  • 🔋 Generator inlet box installation (50A backup power)

What We Don’t Need This Winter:

  • ❌ Radiant floor heat (VEVOR adequate for construction)
  • ❌ Natural gas service (boiler can wait until spring)
  • ❌ Water service (no plumbing fixtures until finish work)
  • ❌ Sewer service (no bathroom until finish work)

When Radiant Heat Is Most Valuable:

  • 🎨 Drywall finishing (mud dries better in warm temps)
  • 🎨 Painting (paint application and curing need warmth)
  • 🔧 Detail/finish work (comfortable temps for precision)
  • 📦 Equipment installation (boiler, HVAC, lift)

All of these happen in spring 2026 - exactly when radiant heat becomes operational.


Options Considered

Option A: All Utilities Now (Rejected)

Approach: Install electrical + gas + water + sewer all in Nov-Dec 2025

Pros:

  • Radiant heat operational by Jan 2026
  • All utilities complete sooner

Cons:

  • ❌ Requires multiple separate trench excavations (electrical separate from others)
  • ❌ Gas/water/sewer share trench - inefficient to dig now when they can be bundled in spring
  • ❌ Peak contractor season (Dec-Jan) = long delays, high costs
  • ❌ Winter excavation challenges (frozen ground, weather delays)
  • ❌ Radiant heat not critical for construction work (VEVOR adequate)
  • ❌ Higher stress, rushed coordination

Rejected because: Cost inefficiency and unnecessary rush for minimal benefit.

Option B: All Utilities Spring (Considered)

Approach: Defer ALL utilities including electrical to spring 2026

Pros:

  • Single coordinated installation in spring
  • Lower overall stress

Cons:

  • ❌ No power for construction tools/lights all winter
  • ❌ Dependent on generator or extension cords from house
  • ❌ Electrical service independent route anyway - can be installed now
  • ❌ Missing opportunity for supplemental electric heat

Rejected because: Electrical service provides significant construction benefits and doesn’t block other utilities.

Option C: Electrical Now, Others Spring (SELECTED) ✅

Approach: Install electrical service in Nov-Dec 2025; install gas/water/sewer/low-voltage in single shared trench spring 2026

Pros:

  • ✅ Power available for construction all winter
  • ✅ Cost-effective: One shared trench for 4 utilities in spring
  • ✅ Better contractor availability (spring vs Dec-Jan peak)
  • ✅ VEVOR heaters adequate for construction work
  • ✅ Radiant heat operational when most beneficial (finish work)
  • ✅ Reduced property disruption (one spring dig vs multiple)
  • ✅ Lower stress, better quality work
  • ✅ Protected mechanical room ready before boiler arrives
  • ✅ No dependency chains blocking progress

Cons:

  • ⚠️ No radiant heat this winter (rely on VEVOR diesel heaters)
  • ⚠️ Cooler working temps (40-50°F vs 55-65°F)

Selected because: Optimal balance of cost, timeline, and practical construction needs.


Implementation Plan

Phase 1: Electrical Service (Nov 7 - Dec 15, 2025)

Week 1 (Nov 7-13):

  • Contact 2-3 licensed electricians for quotes
  • Request: 200A wire, 100A connection, install through existing conduit
  • Timeline: Late November / early December completion
  • Apply for electrical permit

Week 2-3 (Nov 14-27):

  • Select electrician and schedule installation
  • Permit approval
  • Coordinate with Consumers Energy for meter

Week 4-5 (Nov 28 - Dec 15):

  • Electrical service installation
  • Wire pull through conduit
  • Panel installation in mechanical room
  • Connection at house main panel
  • Inspection and approval
  • Service energization

Target: Electrical service operational by mid-December 2025

Phase 2: Shell Work (Dec 2025 - Feb 2026)

Focus on:

  • Mechanical room framing (Stage 3, crew onsite between Nov 24 and Dec 1)
  • Mechanical room insulation (flash-and-batt recommended)
  • Mechanical room drywall (creates protected workspace)
  • Roof completion (Stage 4)
  • Siding and windows (Stage 5)
  • Garage doors installation
  • Use VEVOR diesel heaters for construction heat

Heating Strategy:

  • Two VEVOR Diesel Air Heaters (tested Nov 1, 2025)
  • Expected performance: 40-50°F inside, adequate for construction
  • One unit in mechanical room, one in main bay
  • Electrical service enables supplemental electric heat if needed

Phase 3: Spring Utility Installation (Mar-May 2026)

Preparation (February 2026):

  • Contact 2-3 licensed gas fitters for quotes
  • Contact 2-3 plumbers for water/sewer quotes
  • Coordinate shared trench excavation
  • Apply for gas and plumbing permits

Installation (March-April 2026):

  • Excavate single shared trench (Trench 2 route)
  • Install natural gas line (1” PE pipe through 2” conduit, direct burial to house)
  • Install water line (3/4” PEX through 2” conduit, direct burial to house)
  • Install sewer line (3” PVC, proper slope and depth)
  • Install low-voltage conduit (fiber/network cable)
  • Pressure testing (gas and water)
  • Inspections and approvals
  • Backfill trench

Boiler Installation (April-May 2026):

  • Professional boiler installation in completed mechanical room
  • Connect to radiant manifolds and PEX loops
  • System purging and commissioning
  • Venting verification
  • Begin radiant heat operation

Target: Radiant heat operational by May 2026


Success Metrics

Winter 2025-26 (Electrical Service)

  • ✅ Electrical service energized by mid-December 2025
  • ✅ Mechanical room framing/insulation/drywall complete by end of January 2026
  • ✅ Shell weathertight (roof, siding, windows, doors) by end of February 2026
  • ✅ VEVOR heaters maintain 40-50°F working temps
  • ✅ Power available for all construction tools and lighting

Spring 2026 (Other Utilities)

  • ✅ Single shared trench excavated (one dig, not multiple)
  • ✅ Gas, water, sewer, low-voltage all installed together
  • ✅ Total utility trench cost < 12,000+ for separate trenches)
  • ✅ Boiler operational by May 2026
  • ✅ Radiant heat assists finish work (drywall, painting)

Risk Mitigation

Risk: Electrical Contractor Unavailable in Nov-Dec

Mitigation:

  • Contact 3 electricians immediately (not just 2)
  • If all unavailable by Dec 1, defer to January 2026
  • Still provides power for late winter/spring construction
  • VEVOR heaters sufficient backup

Risk: VEVOR Heaters Insufficient in Extreme Cold

Mitigation:

  • Electrical service enables supplemental electric space heaters
  • Focus on mechanical room completion (can be heated separately)
  • Weatherproofing (roof, siding) reduces heat loss
  • Construction work doesn’t require 65°F temps

Risk: Spring Contractor Delays

Mitigation:

  • Contact contractors in February (6-8 week lead time)
  • Get on schedule early for March-April slot
  • Flexible timeline - May-June also acceptable
  • Finish work can continue with minimal heat (HVAC for cooling)

References

Related Documents:

Key Supporting Evidence:

  • Electricians recommended separate electrical trench (see Trench 1)
  • Shared utility trench is cost-effective (see Trench 2)
  • VEVOR heaters tested and proven adequate (Nov 1, 2025)
  • Frost depth 42” in Michigan - easier excavation in spring

Decision Made By: Project Lead Date Confirmed: 2025-11-07 Next Review: January 2026 (electrical service completion assessment) Status: ✅ Confirmed - Implementation in progress