Location & Layout
- Preferred location:
- Clearances: maintain manufacturer service clearances around all equipment.
- Floor: confirm PEX routing under walls; avoid PEX under anchor points.
- 2025-10-13 contract includes enclosed stair with small mechanical closet; coordinate final wall dimensions before framing to ensure equipment fits.
Critical Dependencies: Boiler Operation Timeline
Boiler installation and operation require sequential completion of multiple systems with significant lead times. Do not expect boiler operation until late December at earliest; early January is more realistic.
Lead Time Items (Must Start Immediately)
-
Electrical Service Installation ⏱️ 2-4 weeks
- Licensed electrician pulls 200A wire through existing underground conduit
- 200A panel installation in mechanical room
- 100A feed from house panel
- Meter installation and energization
- Permit and inspection approval
- Action: Contact licensed electrician immediately for quote and scheduling
-
Natural Gas Service Installation ⏱️ 2-4 weeks
- Licensed gas fitter pulls PE pipe through existing underground conduit
- Underground burial and pressure testing
- Gas line termination and inspection
- Action: Contact licensed gas fitter immediately for quote and scheduling
-
Boiler Venting Route ⏱️ Must be confirmed before framing (Stage 3)
- Boiler manufacturer specifications determine vent route
- Flue vent penetration through wall/roof
- Proper termination clearances per code
- Must be planned during Stage 3 framing
- Action: Review boiler model vent requirements; confirm route before wall framing
Sequential Dependencies
MECHANICAL ROOM FRAME (Stage 3)
↓
Electrical Service Install (licensed electrician)
AND
Gas Service Install (licensed gas fitter)
↓
Boiler Installation (professional)
↓
System Commissioning
↓
RADIANT HEAT OPERATIONAL
Critical Path: All three installations (framing, electrical, gas) must complete before boiler can operate. Any delay cascades.
Notes on Winter Timeline
- High-demand season (Dec 1 - Jan 31): Electrical and gas contractors typically fully booked
- Expect 2-4 week scheduling delays during winter months
- Best-case scenario: Boiler operational mid-December
- Realistic scenario: Late December to mid-January
- Spring scheduling (Mar-Apr): Faster contractor availability if winter operation not critical
Insulation Sequencing Impact
Important: Operating boiler in uninsulated garage is inefficient and wastes fuel. Before or concurrent with boiler startup, complete:
- Mechanical room: Full insulation + drywall (should be done before boiler installation anyway)
- Perimeter wall air-sealing minimum (seal around penetrations, rim joists)
- This dramatically improves boiler efficiency and working comfort
See: Winter Construction Strategy for detailed timing analysis and alternative strategies.
Equipment & Services
- Radiant heat boiler (NG): flue/combustion air, condensate drain, gas, electric.
- Radiant manifolds: supply/return placement, isolation valves, purge points.
- Electrical service/panel: ampacity, working clearances, feeder/conduit path.
- Mini-split provisions: line-set sleeves, condensate drain, outdoor unit disconnect.
- Domestic water/sewer rough-ins (future bath/laundry upstairs).
- Low-voltage: network cabinet, conduit to house.
Penetrations & Rough-Ins
- Gas: sleeve and shutoff location.
- Flue/vent: route and termination per code (sidewall/roof; clearances).
- Condensate: dedicated drain to approved location with trap/neutralizer if required.
- Condensate for mini-split (if indoor head nearby): route with slope.
Electrical
- Dedicated circuits: boiler, pumps, mini-split outdoor unit, server rack, lighting.
- Receptacles: utility outlets at work height; GFCI where required.
Actions
- Freeze mechanical room location and wall layout. — stage:: 2
- Mark PEX-free zones for wall anchors and penetrations. — stage:: 2
- Place sleeves for gas, condensate, line-sets, and low-voltage before pour/framing as needed. — stage:: 2
- Confirm boiler vent route and termination location. — stage:: 4
- Coordinate panel location and service entrance route. — stage:: 3
- Update one-line electrical and hydronic schematics. — stage:: 2
- Confirm PEX tube depth near mechanical room walls; select appropriate anchor length for treated 2×4 sill to slab — stage:: 2
After Build / Commissioning
- Set electrical service/meter and energize panel; label circuits — stage:: 6
- Install boiler and manifolds; commission radiant heat (purge, venting, leak check) — order:: Boiler and Radiant Order — stage:: 6
Procurement
- Order: Boiler and Radiant Order
- Index: Orders Index
Links
- Utilities & sleeves: Utilities & Conduits
- Radiant floor & PEX coordination: Lift
- Insulation: Insulation Execution
- HVAC plan: HVAC Strategy
- Temporary heating (construction phase): Temporary Heating (Winter 2025-26)