Attendees
- Marcus (Hershberger’s)
- Dan Gahagan
Discussion Summary
Framing Timeline
- Marcus estimates his crew will mobilize for framing no earlier than Monday, 2025-11-24.
- Latest start would be Monday, 2025-12-01 if prior commitments or weather delay the crew.
- Materials remain ready; schedule now hinges on crew availability and confirming the foundation cure window is sufficient.
- Marcus committed to calling one week before his crew can start so we have definitive notice.
- His team is currently finishing several other projects; if they stay on track, Nov 24 stands, but any setbacks would push the start to Dec 1.
Coordination Notes
- Mechanical room layout decisions need to stay locked so framing can proceed without rework.
- Electrical service routing decisions should be ready before the crew is onsite (still targeting late Nov scheduling).
Next Steps
- ⧗ Keep mechanical room framing details pinned and accessible for Marcus’s team.
- ⧗ Wait for Marcus’s one-week-out call; if no call by 2025-12-01, reach out for status.
- ⧗ Have electrical service contractor selection finalized before framing begins.