Attendees

  • Marcus (Hershberger’s)
  • Dan Gahagan

Discussion Summary

Framing Timeline

  • Marcus estimates his crew will mobilize for framing no earlier than Monday, 2025-11-24.
  • Latest start would be Monday, 2025-12-01 if prior commitments or weather delay the crew.
  • Materials remain ready; schedule now hinges on crew availability and confirming the foundation cure window is sufficient.
  • Marcus committed to calling one week before his crew can start so we have definitive notice.
  • His team is currently finishing several other projects; if they stay on track, Nov 24 stands, but any setbacks would push the start to Dec 1.

Coordination Notes

  • Mechanical room layout decisions need to stay locked so framing can proceed without rework.
  • Electrical service routing decisions should be ready before the crew is onsite (still targeting late Nov scheduling).

Next Steps

  1. ⧗ Keep mechanical room framing details pinned and accessible for Marcus’s team.
  2. ⧗ Wait for Marcus’s one-week-out call; if no call by 2025-12-01, reach out for status.
  3. ⧗ Have electrical service contractor selection finalized before framing begins.