South Wall Siding Progress with Ladders

Photo Details
- Date: January 1, 2026
- Time: 2:59 PM EST
- Weather: Cloudy, 21°F (feels like 11°F with wind chill). Snow cover on ground.
- Phase: Siding Installation
- Location: 309 E. 7th St., Clare, MI
- View: South wall corner from southeast
Description
South wall showing siding installation progress. Vinyl siding is complete from ground level up to approximately mid-wall height. The upper gable area and dormer face still show Tyvek house wrap awaiting siding completion. Multiple ladders staged for continued work.
Visible Elements
Completed Work:
- Vinyl siding installed on lower wall section (light gray color)
- Service door visible at corner with stone column
- Soffit and fascia complete along eave
- Gable vent visible near peak
Work in Progress:
- Upper gable area showing Tyvek wrap
- Dormer face with Tyvek visible
- Siding transition point clearly visible
Equipment Staged:
- Orange fiberglass extension ladder leaned against wall
- Yellow fiberglass stepladder nearby
- Ladders positioned for accessing upper wall sections
Environment:
- Snow cover on ground
- Adjacent residential structure visible (neighbor’s garage)
- Bare winter trees in background
Construction Progress
Siding crew working up the wall sections methodically. Lower courses complete with clean horizontal lines. Upper sections scheduled for completion tomorrow.