Purpose

Complete bill of materials (BOM) for installing, operating, filling, and maintaining the Navien NCB-E 150 combi boiler selected in Boiler Selection. Serves as the line-item source behind the compressed cost table in that document, and as the master shopping list when the Boiler and Radiant Order is finalized.

Scope: This document lists every component from the gas meter to the manifold supply/return, plus all commissioning chemicals, maintenance consumables, and one-time install tools. It does not cover the PEX manifold or slab loops — those were installed October 2025 and are covered in Radiant Slab Materials Order.


Pre-Install State

Already complete (pre-pour, October 2025):

  • ✅ PEX radiant loops embedded in slab; pressurized and tested (see photo: 2025-10-31 - Pixel - Radiant Heating System Pressure Test)
  • ✅ PEX manifold installed with supply/return headers, balancing valves, and loop purge valves
  • ✅ Slab temperature sensor conduit stubbed up in mechanical closet (see Decisions - Slab Sensor Conduit)
  • ✅ Gas, water, electrical service, sewer, and low-voltage conduits stubbed through slab in mechanical closet footprint

Prerequisites before install (see Mechanical Room for sequencing):

  • ⏳ Mechanical closet framed and drywalled (Stage 3)
  • ⏳ Electrical service energized (licensed electrician pulls 200A through existing conduit)
  • ⏳ Natural gas service installed (licensed gas fitter, spring 2026 per Decision - Electrical Now Utilities Spring)
  • ⏳ Manual J load calculation confirming NCB-E 150 sizing

1. Boiler & Venting

ComponentSpec / ModelNotes
Navien NCB-E 150 combi boiler150,000 BTU input / 120,000 BTU output, 95% AFUEIncludes internal circulator, small stainless buffer tank, internal DHW expansion tank, and integrated 30 psi pressure relief valve
Wall mounting bracketShips with boilerMount to blocking behind drywall
PVC/CPVC intake + exhaust pipe2” Schedule 40Up to 60 ft equivalent length each per Navien manual
Vent termination kitConcentric or two-pipe, sidewallSidewall preferred — avoids roof penetration and flashing complexity
PVC primer + cementLow-VOC, listed for vent usePurple primer is code-required on most jurisdictions
Stainless vent pipe clampsSecure to wall studs every 4 ft
Bird/insect screensOften included in termination kit
Fire-stop collar or intumescent sealantOnly if passing through a fire-rated assemblyMechanical closet wall likely requires this

Estimated subtotal: 2,200–2,800)

2. Gas Supply (Meter to Boiler)

ComponentSpec / ModelNotes
Black iron pipe or CSST (yellow jacket)¾” minimum for NCB-E 150Size per NFPA 54; verify length and fittings don’t derate below required capacity
Manual gas shutoff¾” ball valve, gas-ratedWithin 6 ft of appliance, accessible
Sediment trap / drip legTee + 3” nipple + cap below shutoffRequired by code
Ground-joint unionBetween shutoff and appliance connectorRequired by code; allows boiler removal
Flex connector (CSST or stainless appliance connector)≤6 ft, cannot pass through walls
Yellow gas-rated thread sealantGas-rated PTFE tape OR gas-rated pipe dopeNever use white plumber’s PTFE
ManometerInches-WC, digital (~$40) or borrowFor startup inlet/manifold pressure check

Estimated subtotal: $60–120 (excluding gas line run, which depends on meter-to-closet distance)

3. Potable Water (DHW Side)

ComponentSpec / ModelNotes
Cold inlet shutoff¾” full-port brass ball valveService isolation
Hot outlet shutoff¾” full-port brass ball valveService isolation
Sediment filter housing + cartridge5-micron pleated, ¾” portsProtects DHW heat exchanger from debris
Water softenerSized for household draw + garage demandStrongly recommended for Clare County — hard water is the #1 killer of combi DHW exchangers. Install upstream of boiler on cold inlet
Thermostatic mixing valveHoneywell AM101 or Watts LFL1170, ¾”Code-required scald protection; set to 120°F on outlet
Potable expansion tank2-gal, potable-rated (Amtrol ST-5)Required on closed DHW systems (check valve at meter makes it closed)
Dielectric unionsOnly if transitioning between copper and galvanized/steelPrevents galvanic corrosion
Boiler drain valves (2×)¾” hose-threadOn inlet and outlet for annual descaling
¾” copper Type L or PEX-AFor supply/return runs to fixtures

Estimated subtotal: 400–900)

4. Hydronic Side (Boiler to PEX Manifold)

The manifold is already installed. This section is the plumbing between the boiler and the existing manifold supply/return headers.

ComponentSpec / ModelNotes
Isolation + drain “purge” valves (2×)Webstone Pro-Pal H-53404W or equivalent ¾”Combine shutoff + drain + flush port in one body. Essential for purging air and service isolation. One on supply, one on return between boiler and manifold
Hydronic expansion tankAmtrol Extrol EX-30 (~4.4 gal)Sized to slab loop volume. Required in addition to boiler’s internal DHW tank — the internal tank is DHW-only. Mount on return near boiler with a service valve between tank and system
Combined air + dirt separatorCaleffi DiscalDirtMag 546 series, ¾”Removes microbubbles and magnetic debris in one unit. Mount on supply leaving boiler
Auto air ventFloat-typeIncluded with DiscalDirtMag; replace element at 5–10 years
Manual air bleedersOnly where piping geometry creates high-point air trapsUsually not needed if air separator is well-placed
Pressure-reducing / auto-fill valveWatts 1156F or Bell & Gossett B7-12Maintains 12–15 psi and auto-refills minor losses
Backflow preventerWatts 9D (double-check) or equivalentRequired by MI plumbing code between potable water and closed hydronic loop
Feed shutoff¾” ball valve on fill lineIsolate the fill line from potable system
Pressure + temperature gauge (tridicator)Optional at manifoldBoiler has built-in; extra gauge at manifold aids diagnostics
External circulator pumpTaco 007e or Grundfos UPS15-58 or Alpha 15-55Only if Manual J and pump curve analysis show the NCB-E internal pump is inadequate for the slab loop length. Confirm during commissioning
Hydraulic separator or closely-spaced teesCaleffi SEP4 or field-fabricatedOnly if adding an external secondary circulator (primary/secondary piping)
¾” or 1” copper + fittingsType L sweat or ProPressSize per flow rate from Manual J
Pipe insulation½” or ¾” wall closed-cell foam sleevesOn all hot supply lines
Cushioned pipe hangersPrevents vibration transmission from boiler pump
Pressure relief discharge pipe¾” copper from boiler PRV to within 6” of floorNo valve, no reducer, no cap, no threading at terminus — code requirement

Estimated subtotal: 100–350)

5. Electrical

ComponentSpec / ModelNotes
Dedicated 15A/120V circuitOwn breaker at panelBoiler cannot share circuit
12 AWG Romex or conduitFrom panel to boiler junction
Service disconnect switchRed handle, lockable, within sight of boilerCode-required emergency shutoff, typically at mechanical closet entrance
4”×4” junction box + cord whipFor boiler power connection
24V thermostat wire18/5 or 18/8Boiler to thermostat, plus to zone valves if zoned
ThermostatEcobee, Nest, or Navien NaviLinkNaviLink adds modulating OpenTherm control and Wi-Fi diagnostics
Outdoor reset sensorNavien-compatibleStrongly recommended for slab efficiency — drops supply water temp as outdoor temp rises
Zone control relayTaco SR-504 or Argo AR-84Only if using zone valves instead of multiple circulators
Slab temperature sensor10K thermistorWire to boiler or zone controller via the pre-stubbed conduit

Estimated subtotal: $100–250 (excluding panel circuit labor)

6. Condensate Handling

ComponentSpec / ModelNotes
¾” PVC condensate drain pipe + fittingsContinuous downward slope to drain
Condensate neutralizer kitJJM CN-1 or Axiom NKIT-1Required by MI code for condensing appliances. Raises pH from ~3 to ~7. Limestone media refill every 1–2 years
Condensate pumpLittle Giant VCMA-15ULSOnly if no gravity drain available. Pumps to sink drain or laundry standpipe
Air gap fittingAt drain terminationPrevents backflow from drain into condensate line

Estimated subtotal: 80–130 (with pump)

7. Controls & Safety

ComponentSpec / ModelNotes
CO alarm (hardwired)Mechanical room + loft apartmentMI code requires CO alarms near sleeping areas and within 15 ft of fuel-burning appliances
Emergency boiler shutoff (red handle)At mechanical room entranceWired in-line with disconnect; some jurisdictions require remote location
ABC fire extinguisherMount near mechanical room exitSee Fire Extinguisher Plan
Leak detection pucks (recommended)YoLink, LeakSmart, or Guardian (Elexa)Place under boiler, manifold, and DHW connections. Provides leak localization — whole-house flow monitors only tell you that water is leaking, not where
Whole-house flow monitor + shutoff (house main)Moen Flo or Phyn PlusInstalled on the house main. The garage is fed from the house supply, so a single unit on the house covers both buildings for bursts. See “Leak Detection Strategy” below
Combustible gas detector (optional)Nest Protect CO/gas comboGood practice though not code-required for residential

Estimated subtotal: 100–400)

Leak Detection Strategy

The garage is fed from the house water main, so a Moen Flo (or Phyn Plus) installed on the house side covers both buildings for catastrophic bursts — flow shuts off at the house main regardless of which building the leak is in. Flow monitors can’t tell you where a leak is, so pair the house Flo with wireless leak pucks in the garage mechanical closet (under the boiler, manifold, and water softener connections). Pucks give instant localization via the app so a 3 AM shutoff doesn’t require a cold walk to the garage to diagnose.

Recommended split:

  • House: Moen Flo on the main (~$500). Flow-learning catches slow leaks (running toilets, drip leaks, slab leaks) that pucks miss.
  • Garage: 2–3 pucks in the mechanical closet (~$60–150 total). Catches the high-probability failures: boiler PRV weeping, expansion tank rupture, manifold/fitting leaks, water softener overflow.
  • Manual ¾” ball valve where the garage feed branches off the house supply, so the garage can be isolated without killing house water.

Future: Second Flo for Loft Apartment Conversion

If the loft above is converted to a rental apartment in the future, a dedicated Flo on the garage main becomes worthwhile:

  • Independent usage tracking for tenant billing
  • Isolated shutoff — a tenant-side leak won’t kill house water
  • Flow-learning has enough regular signal to work well once there’s a real occupant

Rough-in accommodation — plan now, install later (near-zero cost):

  • Reserve ~10–12” of straight copper (¾” or 1”) on the garage’s incoming water main, inside the mechanical closet, before any branches. Flo needs ~7” straight run for ¾”, ~10” for 1”.
  • Place a 120V duplex outlet within 4 ft of that reserved section.
  • Install isolation ball valves upstream and downstream of the reserved section during rough-in. Future install becomes a one-hour cut-in with no house-wide shutoff.
  • Keep the location accessible — not buried behind the boiler, softener, or wall.

See Mechanical Room for the layout reservation.

8. Initial Fill & Commissioning Chemicals

ComponentSpec / ModelNotes
System cleanerFernox F3 or Rhomar Pro-Tek 922SCOne-time on initial fill — removes flux, pipe oil, and installation debris before adding inhibitor. Circulate 1–7 days then flush completely
Corrosion inhibitorFernox F1 or Rhomar Pro-Tek 922Permanent addition after cleaner flush. ~1% concentration. Protects mixed-metal system (copper, steel, aluminum heat exchanger, brass valves) from galvanic and oxide corrosion
Propylene glycol (optional)Dowfrost HD or Hercules Cryo-Tek 100Skip unless freeze risk is real. Garage on continuous heat + power doesn’t need it. Glycol reduces heat transfer ~10% and requires pump derating. Never use automotive ethylene glycol — toxic and wrong chemistry
Softened or deionized fill waterHard-water minerals precipitate as scale in the boiler exchanger on first heating cycle. Soft water extends exchanger life significantly
Boiler-fill / purge pumpWayne PC2 or drill-driven pumpPushes water through each loop to purge air. Connects to purge valve hose bibs
Drinking-water-safe garden hoseConnects pump to purge valves
5-gallon bucketPurge discharge catch
Water test stripsHardness, pH, inhibitor concentrationVerify before fill (hardness) and after fill (inhibitor level)

Estimated subtotal: 80–150 per 5-gal if used

9. Maintenance Supplies (Annual / Periodic)

ComponentFrequencyNotes
Descaling flush kitAnnualCalefactio SK2500, Rectorseal Calclean, or Fernox MB-1 — submersible pump + two hoses + bucket. Reuses the installed purge valves
Descaler solutionAnnualWhite vinegar is adequate; Fernox DS-40 or Noritz descaler works faster. 3–4 hour circulation through DHW heat exchanger
Condensate neutralizer refill mediaEvery 1–2 yearsLimestone chips. Test condensate pH with strip; replace media when pH drops below 5
Sediment filter cartridgeEvery 6–12 monthsIf installed upstream of DHW
Inhibitor top-upEvery 3–5 yearsTest concentration with Fernox or Rhomar strips; top up after any drain/refill
Spare flame sensorKeep on hand~$30, 10-minute swap. Common source of “ignition failure” error codes
Spare igniterKeep on hand~$80, 5–10 year service life
Spare pressure relief valveKeep on handCheap insurance — PRVs often weep when old
Gasket kitKeep on handFor combustion chamber inspection or heat exchanger service
Combustion analyzer (optional)One-time purchaseTesto 310 or UEi C157 (~150/visit
Wire brush, stiff nylon brushAnnualClean heat exchanger fins from combustion side
Vacuum with HEPA + brush attachmentAnnualIntake air inlet and boiler cabinet interior

Estimated annual maintenance cost: 150 (pro combustion tune-up if not DIY)

10. One-Time Install Tools

Needed for the install but not “components.” Check existing inventory first; see Tool Purchasing Philosophy for buy-vs-rent framework.

  • Propane torch + lead-free solder + flux (or Milwaukee M18 ProPress jaws if renting)
  • Pipe cutters (½”, ¾”, 1”)
  • Deburring tool
  • Adjustable wrenches, pipe wrenches (18” minimum)
  • Channel locks
  • Torque screwdriver (for boiler gas valve and terminal connections)
  • Manometer + rubber hose (gas pressure test, inches-WC)
  • Multimeter (wiring verification and low-voltage troubleshooting)
  • Stud finder (locate blocking for wall-hung mount)
  • Level, tape measure, drill + hole saws (for vent penetration — 2½” or 3” hole saw)
  • PTFE tape (plumbing) + yellow gas-rated tape
  • Soap bubble gas leak test (or electronic gas sniffer)

Estimated Total Component Budget

SectionLowHigh
Boiler (NCB-E 150)$2,200$2,800
1. Venting$80$150
2. Gas supply (excl. run)$60$120
3. DHW side (excl. softener)$150$350
4. Hydronic side (excl. external pump)$150$250
5. Electrical$100$250
6. Condensate$30$130
7. Controls & safety$80$200
8. Initial fill chemicals$80$150
Install subtotal$2,930$4,400
Water softener (if installed)$400$900
Optional external circulator$100$350
Optional glycol charge$80$150
Optional leak detection$100$400
Project total (with options)$3,610$6,200

Ongoing maintenance: 350 if purchasing combustion analyzer.

This total aligns with the $2,700–3,600 DIY-installed estimate in Boiler Selection Option 1 when excluding the optional items. The softener is the largest optional line and may be installed separately (not tied to boiler project).


Procurement Strategy

Most items ship from HVAC wholesalers (see HVAC Wholesale Buying Guide) or plumbing supply houses. Consider these sources:

  • Navien boiler + Navien-branded accessories: SupplyHouse.com, PexUniverse, or local HVAC wholesaler (contractor pricing often available without a license)
  • Caleffi, Webstone, Amtrol hydronic components: SupplyHouse.com, PexUniverse, Menards
  • PVC venting, gas components: Home Depot, Lowe’s, local plumbing supply
  • Fernox / Rhomar chemicals: SupplyHouse.com, Amazon, or direct from manufacturer
  • Condensate neutralizer: Amazon or SupplyHouse.com

Bundle hydronic components in one order to minimize shipping; order venting locally to avoid PVC freight charges.


References