Completed Slab with Utility Conduits - Wide View

Photo Details
- Date: October 30, 2025
- Time: 11:45 AM EDT
- Weather: Light drizzle clearing, overcast, 49°F. Pour completed successfully.
- Phase: Foundation - Concrete slab pour complete
- Location: 309 E. 7th St., Clare, MI
- View: Ground-level wide view from southeast corner
Description
This wide-angle photo captures the completed 24’ x 40’ concrete foundation slab with utility conduits prominently displayed, providing comprehensive documentation of the finished pour and the integrated utility infrastructure.
Visible Elements
- Completed Concrete Slab:
- Smooth, professionally finished 960 sq ft surface
- Uniform gray concrete with consistent texture
- Level surface across entire garage footprint
- Fresh concrete in early curing phase
- Clean edges along wooden forms
- Autumn leaves scattered on surface
- Utility Conduit System:
- Orange PEX conduits (5 tubes) fanning upward in center area
- Gray PEX conduits grouped separately
- White junction box/mounting assembly at base
- Strategic positioning for electrical services
- Professional installation with proper support
- Clear routing for future wire pulling
- Conduits emerge from approximate center of slab
- Perimeter and Forms:
- Wooden forms defining clean edges
- Forms remain in place for initial curing
- Disturbed soil and excavation around perimeter
- Multiple vertical stakes supporting forms
- Construction debris in foreground
- Site Context:
- White lattice privacy fence on right side
- Neighboring properties with various fencing visible
- Chain-link fence and residential buildings in background
- Trees showing mix of fall colors and bare branches
- Blue sky with excellent afternoon lighting
- Photographer’s shadow extending across slab
Project Milestone
This image documents the successful completion of a major construction milestone:
Foundation Systems Integrated:
- ✓ Under-slab insulation (2” Creatherm)
- ✓ Exterior perimeter insulation
- ✓ In-floor radiant heating (PEX tubing throughout)
- ✓ Fiberglass rebar reinforcement grid
- ✓ Electrical service conduits (5+ orange PEX)
- ✓ Additional utility conduits (gray PEX)
- ✓ Thickened concrete pads for 2-post car lift
- ✓ Temperature sensors for heating control
- ✓ Professional concrete finishing
Construction Achievement
The completed slab represents weeks of careful preparation:
- Excavation and site grading
- Substrate compaction and leveling
- Under-slab insulation installation
- Radiant heating PEX layout (owner-installed)
- Fiberglass rebar grid placement
- Exterior foam insulation
- Utility conduit installation
- Building inspection approval
- Concrete pour and finishing
Next Phases
With the foundation complete, upcoming construction includes:
- Concrete curing (7-28 days for full strength)
- Form removal and cleanup
- Backfilling around perimeter
- Wall framing and vertical construction
- Roof structure
- Electrical rough-in using installed conduits