Completed Front Elevation with Siding and Snow Stops

Completed front elevation with siding, stone panels, and snow stops

Photo Details

  • Date: January 13, 2026
  • Time: 1:00 PM EST
  • Phase: Exterior Completion
  • Location: 309 E. 7th St., Clare, MI
  • View: Front elevation from driveway

Description

Front elevation view of the completed garage exterior showing all siding, stone veneer panels, and snow stops now installed. This represents a major milestone — the exterior work by Hershberger’s framing crew is essentially complete (pending only site cleanup).

Visible Elements

Siding Installation (Complete):

  • Light gray/tan vinyl siding covering all wall surfaces
  • White trim around windows, doors, and corners
  • Both dormers fully sided with matching siding
  • Clean corner details and transitions

Stone Veneer Panels:

  • Versetta Ledgestone (Plum Creek) stone veneer columns
  • Stone panels flanking each of the three garage door openings
  • Stone column next to the service entry door
  • Previously delayed stone panel now installed (was missing Jan 2)

Snow Stops:

  • Metal snow stops installed on standing-seam roof
  • Positioned above the entry door area
  • Prevents snow/ice slides onto walkway below

Garage Door Openings:

  • Three 8-foot tall openings (recently modified from 7-foot)
  • Ready for garage door installation
  • White trim framing each opening

Roof Details:

  • Charcoal standing-seam metal roof
  • Two dormers with windows
  • Ridge line visible
  • Sewer vent boot visible on roof (newly installed)

Entry Door:

  • Half-lite exterior door installed (right side)
  • White trim surround

Site Conditions:

  • Snow cover on ground
  • Scrap pile in foreground (cleanup pending)
  • Metal roofing scraps visible
  • Overcast winter sky

Construction Status

With the completion of this work on January 13, 2026, Hershberger’s framing crew has completed all contracted exterior work:

  • Completed Today:

    • Front siding and stone panel installation (delayed from Jan 2)
    • Snow stops installation
    • Sewer vent stack installation
    • Garage door opening modifications (7’ → 8’ height)
  • Remaining Tasks:

    • Site cleanup / scrap pile removal (dumpster rental)
    • Garage door installation (~1 month out due to reorder)

After the garage doors are installed, the Hershberger’s contract will be complete.