Construction Photo Gallery
Chronological photo documentation of the garage construction project.
October 20, 2025 - Excavation and Forms
Weather: Clear skies, 45-59°F. Ideal conditions for excavation and foundation work.
Foundation excavation, grading, and form installation.
- 2025-10-20 - Excavation Progress
- 2025-10-20 - Foundation Forms (2:12 PM)
- 2025-10-20 - Form Details (2:12 PM)
- 2025-10-20 - Grading View (2:12 PM)
- 2025-10-20 - Evening Progress (6:49 PM)
- 2025-10-20 - Evening Overview (6:49 PM)
October 21, 2025 - Material Delivery
Weather: Rain and drizzle throughout day (morning slight rain, afternoon/evening drizzle), 47-61°F. Storms caused installation work to pause.
Hydronic radiant floor materials delivered to site.
October 22, 2025 - Insulation & PEX Installation
Weather: Light to moderate drizzle all day, 45-51°F. Challenging wet conditions for installation work.
Under-slab Creatherm insulation and radiant heating PEX loops.
- 2025-10-22 - Aerial View - Insulation Complete (5:41 PM)
- 2025-10-22 - Aerial View - Second Angle (6:51 PM)
- 2025-10-22 - Ground Level Overview (7:06 PM)
- 2025-10-22 - Foundation Perimeter & Utility Sleeves (7:06 PM)
- 2025-10-22 - PEX Manifold Installation (7:07 PM)
- 2025-10-22 - Pressure Test Gauge (7:07 PM)
October 25, 2025 - Drone Aerial Photography
Weather: Overcast to clear, 39-53°F. Good flying conditions.
Comprehensive aerial views captured with DJI Phantom 4 Pro showing completed insulation installation and blue PEX slab sensor conduit (owner installed).
- 2025-10-25 - Foundation Insulation - Direct Overhead View
- 2025-10-25 - Garage Foundation and House - Context View
- 2025-10-25 - Complete Property Overview - High Altitude
- 2025-10-25 - Full Property and Neighborhood - Wide Perspective
October 29, 2025 - Exterior Insulation & Fiberglass Rebar
Weather: Clear skies, 45-55°F. Excellent conditions for outdoor prep work.
Drone aerial photography documenting exterior perimeter insulation and fiberglass rebar reinforcement grid installation. Foundation preparation complete and ready for concrete pour.
- 2025-10-29 - Exterior Slab Insulation and Fiberglass Rebar - Aerial View 1
- 2025-10-29 - Exterior Slab Insulation and Fiberglass Rebar - Aerial View 2
- 2025-10-29 - Exterior Slab Insulation and Fiberglass Rebar - Aerial View 3
- 2025-10-29 - Exterior Slab Insulation and Fiberglass Rebar - Aerial View 4
- 2025-10-29 - Exterior Slab Insulation and Fiberglass Rebar - Aerial View 5
- 2025-10-29 - Exterior Slab Insulation and Fiberglass Rebar - Aerial View 6
October 30, 2025 - Concrete Foundation Pour 🎉
Weather: Light drizzle during pour (9:24 AM-11:45 AM), overcast 100% cloud cover, 45-50°F. Challenging conditions but pour completed successfully.
Major Milestone: Complete concrete foundation pour with all utility conduits installed. Finishing work in progress.
- 2025-10-30 - Cement Truck Arrival (9:24 AM)
- 2025-10-30 - Concrete Pour in Progress - Aerial View (9:31 AM)
- 2025-10-30 - Completed Slab - Finished Surface (11:45 AM)
- 2025-10-30 - Utility Conduits Through Slab - Close-Up Detail (11:45 AM)
- 2025-10-30 - Completed Slab with Utility Conduits - Wide View (11:45 AM)
Video Documentation: Real-time video (~1 hour) available at Construction Videos
October 31, 2025 - Post-Pour Finishing & Testing
Weather: Clear to overcast, 38-53°F. Good conditions for finishing work and pressure testing.
Cement contractor completed finishing work including control joint saw cutting, form removal, and perimeter backfilling. Radiant heating system pressure testing verified system integrity.
- 2025-10-31 - Slab Finishing Complete - Saw Cuts and Perimeter Fill (1:50 PM)
- 2025-10-31 - Finished Slab with Conduits - Northwest View (1:51 PM)
- 2025-10-31 - Radiant Heating System Pressure Test (1:51 PM)
November 1, 2025 - Temporary Heat Prep & Family Milestone
Weather: Clear to overcast, 38-51°F. Good conditions for site work.
Temporary heat planning and a personal touch added to the slab before framing begins.
November 3, 2025 - Final Grading & Site Cleanup
Weather: Clear and windy afternoon (14-18 mph winds from west), 42-57°F. Good conditions for final grading work.
Final day of cement contractor work creating a smooth level entry to the garage slab.
- 2025-11-03 - Site Grading Progress (1:54 PM)
- 2025-11-03 - Grading Detail View (1:54 PM)
- 2025-11-03 - Site Grading After Concrete Crew (4:15 PM)
November 18, 2025 - Roof Trusses Delivered 🎉
Weather: Cloudy, 39°F (feels like 36°F). Good conditions for material delivery.
Major Milestone: Engineered roof trusses delivered to site, staged on cured concrete slab. Framing crew mobilization target: December 3, 2025. Complete engineering documentation package received with delivery. Each truss includes QR code tag linking to exact specifications and engineering drawings.
- 2025-11-18 - Roof Trusses Delivered to Site (11:36 AM)
- 2025-11-18 - Truss Identification Tag with QR Code (1:02 PM)
- 2025-11-18 - Truss Layout Schematic - Large Format (1:04 PM)
Engineering Documents: Truss Engineering Drawings (8 pages) • Loading Ticket & Inventory
Framing Update: Marcus Call - Dec 3 Start Date
December 3, 2025 - Framing Kickoff
Weather: Overcast, 18-24°F. Snow cover on site from overnight accumulation; cold but workable conditions for framing kickoff.
Framing crew stood first-floor walls, set headers, and staged sheathing, hangers, and sill gaskets. Material invoices captured for records.
- 2025-12-03 - Early Morning Lumber Delivery (7:21 AM)
- 2025-12-03 - First Floor Walls Rising (1:12 PM)
- 2025-12-03 - Framing Progress from House Window (1:13 PM)
- 2025-12-03 - Ridged Sill Plate Gasket (3:23 PM)
- 2025-12-03 - Interior Bracing and Bottom Plate Anchor (3:29 PM)
- 2025-12-03 - Front Elevation Framing with Center Bay Bracing (3:30 PM)
- 2025-12-03 - Framing Progress Checkpoint (3:37 PM)
- 2025-12-03 - Materials Invoice (Adhesive, OSB, Foam) (3:42 PM)
- 2025-12-03 - Materials Invoices (Framing Lumber & Hardware) (3:42 PM)
- 2025-12-03 - Materials Invoices (Alternate Capture) (3:42 PM)
- 2025-12-03 - OSB Stacks Staged for Framing (3:43 PM)
- 2025-12-03 - Framing Lumber on Sawhorses (3:43 PM)
- 2025-12-03 - OSB Grade Stamp (3:43 PM)
- 2025-12-03 - Joist Hanger Hardware Box with Invoices (3:44 PM)
- 2025-12-03 - Simpson LUS28Z Joist Hanger (3:44 PM)
- 2025-12-03 - Simpson HGUS48 Hanger (3:44 PM)
December 4, 2025 - Roof Trusses Set & Dormer Framing
Weather: Overcast clearing to partly sunny, then clear by afternoon. Temperature range 10-21°F, NW winds 5-10 mph. Snow cover on site from Dec 1-3 storms; ideal visibility for photography as skies cleared throughout the day.
Equipment staged for snow clearing, then roof trusses set and dormer framing began. Significant progress on loft joist installation with hangers and blocking.
- 2025-12-04 - Gehl RT215 Track Loader Arrival (7:57 AM)
- 2025-12-04 - Hydraulic Auger Attachment Staged (7:57 AM)
- 2025-12-04 - Truss Set with Loader Assist (9:15 AM)
- 2025-12-04 - Front Elevation with Roof Trusses Set (12:09 PM)
- 2025-12-04 - Left Elevation Truss Alignment (12:13 PM)
- 2025-12-04 - Afternoon Framing Overview from House (2:53 PM)
- 2025-12-04 - Dormer Framing in Place (2:56 PM)
- 2025-12-04 - Loft Joists and Hanger Installation (2:57 PM)
- 2025-12-04 - Titebond Construction Adhesive (2:57 PM)
- 2025-12-04 - Interior Loft Framing Progress (2:58 PM)
- 2025-12-04 - RT215 Control Console Detail (3:11 PM)
December 8, 2025 - Roof Sheathing & Weatherproofing
Weather: Clear winter sun in morning, partly cloudy afternoon. Temperature 20-26°F with full snow cover on site. Excellent conditions for roofing progress.
Roof sheathing lifted to dormers, main roof planes sheathed, and weatherproofing applied. Synthetic underlayment installed across roof surfaces; Tyvek house wrap applied to dormer faces.
- 2025-12-08 - Roof Sheathing Lift to Dormers (12:13 PM)
- 2025-12-08 - Underlayment and Tyvek-Wrapped Dormers (3:23 PM)
Video Documentation: Time-Lapse Video
December 9, 2025 - Loft & Stair Interior Progress
Weather: Cloudy, 33°F (feels like 25°F). Overcast skies with snow cover on roof and ground; interior work protected by completed shell.
Site visit documenting interior loft space and stair framing progress. Stair rough-in to loft complete with landing and blocking; loft floor fully decked with OSB and knee walls framed; dormer openings framed and ready for windows.
- 2025-12-09 - Loft Stair Framing with Helper (3:02 PM)
- 2025-12-09 - Loft Open Room Under Roof (3:03 PM)
- 2025-12-09 - Dormer View from Loft Interior (3:03 PM)
- 2025-12-09 - Exterior Dormer Check from Driveway (3:13 PM)
Video Documentation: Time-Lapse Video
December 11, 2025 - Metal Roof Installation & Material Delivery
Weather: Cloudy, 26-30°F. Cold winter afternoon with snow cover; good conditions for roofing work.
Major Progress: Standing-seam metal roof installation in progress on main roof planes and dormers. Roofing crew working throughout the day with panels nearly complete by late afternoon. Significant material delivery including all windows, exterior door, decorative stone panels, and siding prep materials.
Roofing Progress (12:13 PM - 4:53 PM):
- Crew Installing Standing-Seam Roof (12:13 PM)
- Metal Roof Nearly Complete - Front Elevation (4:50 PM)
- Dormer Roof Tie-In Closeup (4:50 PM)
Roofing Materials Staged:
- Vent (4:50 PM)
- Simpson Strong-Tie Fastener Box (4:51 PM)
- Roofing Hardware and Foam Closures (4:53 PM)
- Ridge Vent Foam and Membranes (4:53 PM)
- Foam Closure Label (ASH-25-25-06) (4:53 PM)
- [[PXL_20251211_215329510.md|#10 x 2.5” Roof Screws with SS Washers (4:53 PM)]]
Window Delivery (8 units total from ABC Supply):
- Egress Window Unit Delivered (4:52 PM)
- Window Label - Egress Unit 39½” x 59½” (4:52 PM)
- Stack of Standard Windows (7x) (4:52 PM)
- Window Label 35½” x 35½” (1 of 7) (4:52 PM)
- Window Label 35½” x 35½” (2 of 7) (4:52 PM)
- Window Label 35½” x 35½” (3 of 7) (4:52 PM)
- Window Label 35½” x 35½” (4 of 7) (4:52 PM)
- Window Label 35½” x 35½” (5 of 7) (4:52 PM)
- Window Label 35½” x 35½” (6 of 7) (4:52 PM)
- Window Label 35½” x 35½” (7 of 7) (4:52 PM)
Exterior Shell Materials Delivered:
- Exterior Door Delivered (Half-Lite) (4:51 PM)
- Decorative Stone Panels Delivered (4:51 PM)
- Tyvek HomeWrap Roll Onsite (4:52 PM)
- Dupont Flashing Tape Delivery (4:51 PM)
- Housewrap, Trim, and Fasteners Staged (4:52 PM)
Interior Staging:
December 12, 2025 - Exterior Shell Complete 🎉
Weather: Partly cloudy to overcast, 30°F (feels like 23°F with wind chill). Snow cover on ground; cold but clear conditions for final exterior work.
Major Milestone: Exterior shell complete — metal roof fully installed on main roof and dormers, all windows set (8 total), main entry door installed, vented soffits in place, and Tyvek HomeWrap fully covering walls. Building is now weathertight and ready for siding installation scheduled for Monday.
Exterior Progress:
- Front Elevation with Metal Roof Completed (1:58 PM)
- Wrapped Shell with Metal Roof Complete (3:24 PM)
- Vented Soffit and Fascia Along Front Eave (3:30 PM)
Window Installation (All 8 Units):
- Interior View - Main Floor Windows Set (3:25 PM)
- First-Floor Window Install Detail (3:26 PM)
- Window Label and QR for Finish Instructions (3:26 PM)
- Loft Gable Window Installed (3:27 PM)
- Loft Gable Window Detail (3:27 PM)
- Dormer Window Above Stair Opening (3:27 PM)
Entry Door Installation:
December 18, 2025 - Electrical Trenching Attempt
Weather: Cloudy, 50°F. Unusually warm December day with thawing conditions near structures, but ~10” frost depth in open ground.
Electrical Service Update: SLS Electric arrived around 3 PM to begin trenching for the 200A house-to-garage underground power line. The Ditch Witch successfully trenched and buried the wire in the section along the house foundation where ground was thawed (~6-8 ft left above ground at house meter for panel connection). However, the open area between house and garage had approximately 10 inches of frozen ground. Even the largest rental backhoe made only 3 feet of progress in 30 minutes. Work halted until spring 2026 — wire spool stored at terminus for completion.
Equipment & Materials:
Trench Progress (House Section):
- Trench View Toward Garage (4:42 PM)
- House Foundation Connection Point (4:42 PM)
- Trench Full Length Along House (4:42 PM)
- Ditch Witch at Trench End (4:43 PM)
Frozen Ground Challenge:
December 20, 2025 - Pre-Christmas Documentation
Weather: Mostly cloudy, 33°F, windy with gusts to 30 mph. Snow cover on ground.
Construction Status: Work paused for Christmas break. Building shell complete and weathertight. Documenting materials used and current exterior state before siding installation resumes.
Materials Documentation:
- Simpson Strong-Tie Sheathing Clips (4:05 PM)
- DuPont FlexWrap Roll (4:05 PM)
- DuPont Flashing Tape Label (4:05 PM)
Exterior Shell Progress:
- South Wall with Tyvek HomeWrap (4:11 PM)
- South Wall Long View with Snow (4:11 PM)
- Window Flashing Detail - Protecto Wrap (4:11 PM)
- Window Detail with FlexWrap Sill (4:11 PM)
- South Wall Windows Overview (4:11 PM)
December 25, 2025 - Rafter Documentation for Insulation Planning
Weather: Cloudy, 21°F. Cold Christmas afternoon with snow cover.
Purpose: Interior documentation of roof truss system for future insulation planning. Photos capture truss spacing, gusset plate locations, ridge area geometry, and accessible cavity depths.
Roof Truss Interior Views:
- Gable End Corner Detail (3:22 PM)
- Gable End Corner - Alternate (3:22 PM)
- Trusses and Loft Framing Overview (3:22 PM)
- Roof Peak and Ridge Beam Detail (3:23 PM)
- Ridge Perspective - Multiple Trusses (3:24 PM)
- [[PXL_20251225_202521723.MP.md|Gable End Truss with ID Tag #123907 (3:25 PM)]]
- Loft Ceiling Trusses - Wide View (3:25 PM)
Related: Insulation Planning
January 1, 2026 - Siding Progress
Weather: Cloudy, 21°F (feels like 11°F with wind chill). Snow cover on ground.
Construction Status: Siding installation in progress. West and north walls complete; front and south walls partially complete. Crew reports siding will be finished tomorrow (January 2). Garage door installation scheduled for January 6 - final task remaining.
Video Documentation: Time-Lapse Video
Exterior Progress:
- Front Elevation - Siding in Progress (2:58 PM)
- Service Door and Bay Detail (2:59 PM)
- South Wall Siding with Ladders (2:59 PM)
- West Wall Siding Complete (3:00 PM)
- North Wall Siding with Windows (3:00 PM)
- North Wall Corner and Soffit Detail (3:00 PM)
Stone Veneer Details:
Interior Views:
January 2, 2026 - Siding Delayed - Material Shortage
Weather: Clear skies, 18°F (feels like 8°F with wind chill). Snow cover on ground.
Construction Status: Front siding installation incomplete due to material shortage — replacement stone panel not in stock. Since siding must be installed from bottom to top, front wall work cannot proceed until the missing stone panel arrives. All other areas complete including side walls, rear wall, both dormers, and exterior outlet housing installation.
Outstanding Items (to be completed on return visit):
- Replacement stone panel delivery and front wall siding completion
- Snow guards installation on roof above entry door
- Sewer vent installation through roof
Video Documentation: Time-Lapse Video
Exterior Progress:
- Front Elevation - Siding Incomplete (5:28 PM)
- Front Dormer Detail - Siding Complete (5:28 PM)
- Rear Side Elevation - Siding Complete (5:29 PM)
- External Outlet Housing Installed (5:29 PM)
January 5, 2026 - Garage Door Installation Canceled - Wrong Size Ordered
Weather: Overcast, mid-30s°F. Cold winter morning.
Construction Status: Garage door installer arrived Monday morning to install the three garage doors. Upon unloading, he discovered a sizing mismatch. Initially thought to be a door ordering error, it was later determined (Jan 13) that the doors were ordered correctly at 8 feet tall but the framing crew had been given incorrect prints showing 7-foot openings. The installer loaded the doors back onto his truck pending resolution.
Silver Lining: The installer left the three Genie 6170H-B Professional Line garage door openers on-site, staged inside the garage for future installation.
Photos:
January 13, 2026 - Front Siding Complete & Door Opening Modifications 🎉
Weather: Overcast, 30s°F. Cold winter afternoon with snow cover.
Major Milestone: Hershberger’s framing crew completed all remaining exterior work. The front siding and stone panels (delayed since Jan 2) are now fully installed. The crew also modified the garage door openings from 7 feet to 8 feet in height to match the correctly-ordered doors — resolving the issue discovered on January 5. It turned out the contractor had been given incorrect prints during the build phase; the doors were ordered at the correct 8-foot height all along.
Work Completed Today:
- Front wall siding installation (previously delayed due to missing stone panel)
- Versetta Ledgestone stone veneer panels installed on all garage door columns
- Snow stops installed on roof above entry door
- Sewer vent stack routed through roof
- Garage door openings modified from 7’ to 8’ height
Remaining Items:
- Site cleanup / scrap pile removal (dumpster rental)
- Garage door installation (awaiting delivery, ~1 month)
After garage door installation, the Hershberger’s contract will be complete.
Exterior Completion:
Interior Documentation:
- Modified Garage Door Openings - Interior View (12:59 PM)
- Sewer Vent Stack Through Roof Trusses (12:59 PM)
January 15, 2026 - Electrical Trench Ground Thawing
Weather: Clear skies, 18°F (feels like 7°F with wind chill). Cold conditions requiring ground thawing.
Electrical Service Update: SLS Electric deployed passive concrete curing blankets (insulation, not electrically heated) to thaw the frozen ground between the house and garage. The blankets work by absorbing solar radiation, preventing further frost penetration, and allowing geothermal heat from below to warm the soil. Estimated timeline: 2-4 weeks (late January to early February) depending on weather. Once thawed, they will complete the underground trench for the 200A electrical service line (partially completed December 18, 2025).
January 21, 2026 - Garage Doors Installed 🎉
Weather: Cloudy, 30°F (feels like 21°F with wind chill). Snow cover on ground.
Major Milestone — Initial Build Complete: All three garage doors (8’x9’ insulated white with windows) and Genie 6170H-B Professional Line openers installed. Openers feature battery backup, allowing door operation despite garage not yet having electrical service. Hershberger’s contract work is now complete pending only site cleanup (dumpster rental for scrap pile removal).
Installation Progress (Morning):
- Interior View - Installation in Progress (9:46 AM)
- Interior View - Alternate Angle (9:46 AM)
- Exterior - Two Doors Installed (9:48 AM)
- Third Door Panels Staged (9:49 AM)
- All Three Doors Complete - Elevated View (10:17 AM)
Completed Installation (Afternoon):
- Completed Garage - Front Elevation (2:43 PM)
- All Three Doors - Interior View (3:20 PM)
- Door Operational Test - Battery Backup Working (3:21 PM)
January 27, 2026 - Building Inspector Visit
Weather: Cloudy, 19°F (feels like 5°F with wind chill). Cold winter afternoon.
Inspection Result: The building inspector visited and stated everything looked good, with one requirement noted: a guardrail must be installed at the stairwell opening in the loft to meet code requirements for fall protection.
Inspector Requirement Documentation:
January 29, 2026 - Construction Planning
Weather: Partly cloudy, 14°F high, -10°F low overnight. Extreme cold continues.
Planning: Created visual mockup of proposed stairwell wall construction plan based on inspector requirements and future bathroom layout considerations.
Construction Plan Mockup:
February 11, 2026 - Cement Blankets Removed — Ground Still Frozen
Weather: Mostly cloudy, ~30°F. Snow cover on ground; continued cold winter conditions.
Electrical Service Update: SLS Electric (Steve) visited the site on February 11 and removed the concrete curing blankets that had been deployed since January 15 (28 days). Despite nearly a month of passive thawing, the ground underneath the blankets is still frozen solid. The sustained extreme cold throughout January and early February — with highs rarely reaching freezing and lows as cold as -10°F — completely negated the passive thawing approach. Electrical trench completion is now deferred to spring thaw (estimated late March to April 2026). Photo taken February 12 documenting the site after blanket removal.